AD Weekly Friday - 2017 Scheduling Meeting/Weekly Summary

US/Central
One West (Wilson Hall)

One West

Wilson Hall

Description
Weekly Scheduling, Planning and Status 
Performance Plots
Meetings will be held on Monday, Wednesday, and Friday of each week.
AD Weekly Friday - 2017 Scheduling Meeting/Weekly Summary (05 May 2017)

Crew Chief

  • See slide. MI transductor electronics issue. Vacuum pump changout on RFQ. Tuning in progress.
Operations Coordinator
  • See Slide.
Linac
  • Referred to the RFQ vacuum pump replacement. Otherwise running well.
Booster
  • See slide. Running well.
Main Injector & Recycler
  • See slides. Discussion about MI-60N ground fault/buss work issues.
NuMI
  • Running well.
NuMI Experiments
  • Running well.
Booster Neutrino
  • Running well.
BNB Experiments
  • Running well.
Muon Rings
  • Working on shunts this morning. May take beam this afernoon. Still a number of things not ready for coasting beam in the Delivery ring. Good news - EE support able to pulse Pmag. Plan to take low power beam to target if applicable.
MTA
  • In between experimental runs, waiting for approval. Cavity is running successfully.
SY120, Neutrino Muon, Meson Test, Meson Center
  • Thanks to MI & MSD for vacuum work in MI-52 region. Tuesday Code 1 at SSB fire alarm for building ceiling heater failure. No damage at SSB other than the heater. Meson beamline off yesterday for experimets install. (M03 & MC6?) Commisioning of M03 exp. went well last night. Thanks to ops for beam setup & tuning. Installed temperature sensor on M01 target. FESS borescoped F2 sump line.
SY120 Experiments
  • Thanks to Michael & Adam for help with M03 experiment installation. Six (6) experiments installed! Maybe a record in MI Fixed target era.
FAST
  • Transverse profile monitor installation continues. Vacuum techs removed xray equipt. from 50 Mev line. Controller board for chiller died. New board installation today. ODH class 1 next week.
PIP-II Injector Test
  • Shutdown continues. Most girders are populated. Meson 3rd cavity installed & under vacuum. Maybe testing next week.
Alignment
  • Provided support for CMTF - Laser scanning.
Controls
  • Repeater power supply failure @ F-27.
Cryo
  • Meson frig is cold. Transfer line is filled with LHe. Vacuum running. Some issues with discharge water pressure, FESS is investigating. Decontam SGC. G-1 wet engine failed. Felts not properly filled with grease. CMTF is cold and running well. NML, FAST Lab B ready. MTA cold and running well.
ES&H
  • MI-12 investigation continues.
EE Support
  • Discussion about the MI transductor electronics replacement. MI 60 S water on floor, 2 hr opt
Instrumentation
  • Found problem with booster toroid, loose solder connection.
Mechanical & Fluids
  • IP829 faulted. MC7 chiller under repair. Under vac today adding refrigerant later.
RF
  • MI, RR & BRF running well.
FESS
  • Awaiting details on Comm Ed switch.
Summer Shutdown 2017
  • Still some manpower issues. Overall in fairly good shape. Short maybe 3 or 4 people. Worklist reminder.
Miscellaneous
  • Discussion on hot Comm Ed switch. See Slides. Main plan - shutdown & access day on Monday May 15th IF schedule holds up.
There are minutes attached to this event. Show them.
    • 09:00 09:03
      Crew Chief 3m One West

      One West

      Wilson Hall

      Slides
      See slide.  MI transductor electronics issue.  Vacuum pump changout on RFQ.  Tuning in progress.
    • 09:03 09:06
      Operations Coordinator 3m One West

      One West

      Wilson Hall

      Slides
      See Slide.
    • 09:06 09:09
      Linac 3m One West

      One West

      Wilson Hall

      Referred to the RFQ vacuum pump replacement. otherwise running well.
    • 09:09 09:12
      Booster 3m One West

      One West

      Wilson Hall

      Slides
      See slide.  Running well. 
    • 09:12 09:15
      Main Injector & Recycler 3m One West

      One West

      Wilson Hall

      Slides
      See slides.  Discussion about MI-60N ground fault/buss work issues.
    • 09:15 09:18
      NuMI 3m One West

      One West

      Wilson Hall

      Running well.
    • 09:18 09:21
      NuMI Experiments 3m One West

      One West

      Wilson Hall

      Running well.
    • 09:21 09:23
      Booster Neutrino 2m One West

      One West

      Wilson Hall

      Running well.
    • 09:23 09:24
      BNB Experiments 1m One West

      One West

      Wilson Hall

      Running well.
    • 09:24 09:26
      Muon Rings 2m One West

      One West

      Wilson Hall

      Working on shunts this morning.   May take beam this afernoon.  Still a number of things not ready for coasting beam in the Delivery ring.  Good new - EE support able to pulse Pmag.  Plan to take low power beam to target if applicable.
    • 09:27 09:29
      MTA 2m One West

      One West

      Wilson Hall

      In between experimental runs, waiting for approval.  Cavity is running successfully.
    • 09:29 09:32
      SY120, Neutrino Muon, Meson Test, Meson Center 3m One West

      One West

      Wilson Hall

      Thanks to MI & MSD for vacuum work in MI-52 region.   Tuesday Code 1 at SSB fire alarm for building ceiling heater failure. No damage at SSB other than the heater.   Meson beamline off yesterday for experimets install. (M03 & MC6?)  Commisioning of M03 exp. went well last night.  Thanks to ops for beam setup & tuning.  Installed temperature sensor on M01 target. FESS borescoped F2 sump line.
    • 09:32 09:35
      SY120 Experiments 3m One West

      One West

      Wilson Hall

      Thanks to Michael & Adam for help with M03 experiment installation.  Six (6) experiments installed! Maybe a record in MI Fixed target era.
    • 09:35 09:38
      FAST 3m One West

      One West

      Wilson Hall

      Transverse profile monitor installation continues.  Vacuum techs removed xray equipt. from 50 Mev line. Controller board for chiller died. New board installation today. ODH class 1 next week.
    • 09:38 09:40
      PIP-II Injector Test 2m One West

      One West

      Wilson Hall

      Shutdown continues. Most girders are populated.  Meson 3rd cavity installed & under vacuum. Maybe testing next week.
    • 09:40 09:42
      Alignment 2m One West

      One West

      Wilson Hall

      Provided support for CMTF - Laser scanning.
    • 09:42 09:45
      Controls 3m One West

      One West

      Wilson Hall

      Repeater power supply failure @ F-27.
    • 09:45 09:47
      Cryo 2m One West

      One West

      Wilson Hall

      Meson frig is cold. Transfer line is filled with LHe.  Vacuum running.  Some issues with discharge water pressure,  FESS is investigating.  Decontam SGC.  G-1 wet engine failed. Felts not properly filled with grease.  CMTF is cold and running well.  NML, FAST Lab B  ready. MTA cold and running well.
    • 09:47 09:50
      ES&H 3m One West

      One West

      Wilson Hall

      MI-12 investigation continues.
    • 09:50 09:52
      EE Support 2m One West

      One West

      Wilson Hall

      Discussion about the MI transductor electronics replacement. MI 60  S water on floor, 2 hr opt
    • 09:52 09:54
      Instrumentation 2m One West

      One West

      Wilson Hall

      Found problem with booster toroid, loose solder connection.
    • 09:54 09:55
      Mechanical & Fluids 1m One West

      One West

      Wilson Hall

      IP829 faulted. MC7 chiller under repair.  Under vac today adding refrigerant later.
    • 09:55 09:56
      RF 1m One West

      One West

      Wilson Hall

      MI, RR & BRF running well.
    • 09:56 09:58
      FESS 2m One West

      One West

      Wilson Hall

      Speakers: Gilbert, Shirley, Sprosty
      Awaiting details on Comm Ed switch.
    • 09:58 09:59
      Summer Shutdown 2017 1m One West

      One West

      Wilson Hall

      Speaker: Mr Cons Gattuso (Fermi Lab)
      Still some manpower issues. Overall in fairly good shape.  Short maybe 3 or 4 people.  Worklist reminder.
    • 09:59 10:00
      Miscellaneous 1m One West

      One West

      Wilson Hall

      Slides
      Discussion on hot Comm Ed switch.  See Slides.  Main plan -  shutdown & access day on Monday May 15th IF schedule holds up.