Mon-Thurs Accelerator Scheduling Meeting
9 AM Meeting (22 May 2017)

Crew Chief Operations Summary

  • See Slide.
Linac
  • Marx's mod #5 issue, otherwise good weekend. Would like to install Laser notcher this week. More info to follow.
Booster
  • Will use $17 cycles for studies. BRF #10 issues, need 5-10 minutes oppertunistic. BRF#7 tuner dripper. Booster LCW supply & return pressure issues. BRF#3 asprin tab issue. Thanks to ops for access #10.
Booster Neutrino
  • Running well. 5Hz running issue. Wll continue 5Hz. operation.
BNB Experiments
  • Microboone cryo problem. May be contanimation issues. Rep-rate question asked.
Main Injector & Recycler
  • 520 vacuum issue discussed. Suggesting startup after extended DT (2+hrs) at slower rep-rate. (i.e. Numi cycle every 10 seconds untill @ equivalent # turns for max wattage, then increase rep-rate.)
NuMI
  • Kicker failure Friday, EE support fixed. Controls issues.
NuMI Experiments
  • Running well. Noticed reduction in intensity.
Muon Rings
  • Last week, ready to run. First time able to test critical device power supplies. One needed new contactor. Friday evening circulated 3 Gev beam, set up abort kicker with rough timing. Today try running 8 Gev beam, RF capture & closed orbit on agenda.
SY120
  • Ran well over the weekend. Reminder about outside temperature variation and the need to turn on NS2 sprinklers for extra cooling. Manual mode by Adam W. until PLC work to automate.
SY120 Experiments
  • Seaquest doing OK, MCenter Lariet still down with wire chamber. Will also replace filters. Mtest ready to take beam.
ES&H
  • Nothing to report.
EE Support
  • Friday replaced VCB @ MI-30 Lower PS. Kicker, some arcing on charging tank.
Mechanical
  • MI-40 Abort LCW pump #2 placed in 'hand' mode to run. Work order in for final repair of motor control MCC.
RF
  • BRF #3 asprin tab replaced this AM. BRF10 ready to be reconnected to anode ps (oppertunistic) Need 15 minutes no bean in MI for MIRF8 diagnostic.
MTA
  • Will be running cavity all week.
Controls
  • Muon crate $1F cycling, PS replaced. (AP10)
Instrumentation
  • Nothing to add.
FESS
  • No report.
There are minutes attached to this event. Show them.
    • 09:00 09:01
      Crew Chief Operations Summary 1m
      Slides
      See Slide.
    • 09:01 09:02
      Linac 1m
      Marx's mod #5 issue,  otherwise good weekend.   Would like to install Laser notcher this week. More info to follow.
    • 09:02 09:03
      Booster 1m
      Will use $17 cycles for studies.  BRF #10 issues, need 5-10 minutes oppertunistic.  BRF#7 tuner dripper. Booster LCW supply & retrun pressure issues. BRF#3 asprin tab issue.  Thanks to ops for access #10.
    • 09:03 09:04
      Booster Neutrino 1m
      Running well.  5Hz running issue.  Wll continue 5Hz.  operation.
    • 09:04 09:13
      BNB Experiments 9m
      Microboone cryo problem. May be contanimation issues. Rep-rate question asked. 
    • 09:13 09:18
      Main Injector & Recycler 5m
      520 vacuum issue discussed. Suggesting startup after extended DT (2+hrs) at slower rep-rate. (i.e. Numi cycle every 10 seconds untill @ equivalent # turns for max wattage,  then increase rep-rate.)  
    • 09:18 09:19
      NuMI 1m
      Kicker failure Friday, EE support fixed.  Controls issues.
    • 09:19 09:20
      NuMI Experiments 1m
      Running well.  Noticed reduction in intensity.
    • 09:20 09:21
      Muon Rings 1m
      Last week, ready to run.  First time able to test critical device power supplies.  One needed new contactor.  Friday evening circulated 3 Gev beam, set up abort kicker with rough timing.  Today try running 8 Gev beam, RF capture & colsed orbit on agenda.
    • 09:21 09:22
      SY120 1m
      Ran well over the weekend.  Reminder about outside temperature variation and the need to turn on NS2 sprinklers for extra cooling. Manual mode by Adam W. until PLC work to automate.
    • 09:22 09:23
      SY120 Experiments 1m
      Seaquest doing OK, MCenter Lariet still down with wire chamber.  Will also replace filters. Mtest ready to take beam.
    • 09:24 09:25
      ES&H 1m
      Nothing to report.
    • 09:26 09:27
      EE Support 1m
      Friday replaced VCB @ MI-30 Lower PS.  Kicker, some arcing on charging tank.
    • 09:27 09:28
      Mechanical 1m
      MI-40 Abort LCW pump #2 placed in 'hand' mode to run.  Work order in for final repair of motor control MCC.
    • 09:28 09:29
      Fluids 1m
    • 09:29 09:30
      RF 1m
      BRF #3 asprin tab replaced this AM.  BRF10 ready to be reconnected to anode ps (oppertunistic) Need 15 no bean in MI for MIRF8 diagnostic.
    • 09:30 09:31
      MTA 1m
      Will be running cavity all week.
    • 09:31 09:32
      Controls 1m
      Muon crate $1F cycling, PS replaced. (AP10)
    • 09:32 09:33
      Instrumentation 1m
      Nothing to add.
    • 09:33 09:34
      FESS 1m
      No report.
    • 09:35 09:36
      Miscellaneous 1m