Running well but down 1 RF station.
Would like to change the modulator on station 9 today to have it for the weekend.
Laser Notcher/Cogging studies were done yesterday. Plan to do more this afternoon.
Next week request some end of run studies.
Next Tuesday plan to work on RF station 21 during the maintenance period.