Mu2e ESS engineering meeting

US/Central
Drafting Meeting Room

Drafting Meeting Room

Vladimir Nagaslaev (Fermilab)

Tuesday, October 13, 2015

 
  1. Dave is back after sick leave
    1. Will follow up on the HV cable
  2. Identified springs
  3. Options for attaching foils to shims:
    1. Brazing
    2. Crimping
    3. Quote for brazing: $3,862 for 100 foils/20 days  (Morgan/Wesgo)
  4. Mike: delay in drawing processing due to new policy of drawing vetting
    1. Wanted to talk to Mayling  -- did not, there was someone in her office
    2. Turned out – there is a second person assigned to back up Dennis
  5. Matt wasn’t able to fine W25%Re foil vendor
  6. Matt’s time in October: could be more available but LEBT EM is still not complete
There are minutes attached to this event. Show them.
The agenda of this meeting is empty