LArSoft Coordination Meeting

US/Central
Conjectorium (WH3NE)

Conjectorium

WH3NE

Description
ReadyTalk: +1 (866) 740-1260 (U.S. toll free), +1 (303) 248-0285 (U.S. toll number)
Code: 886 7778

At Fermilab:  WH3NE

Present: Ruth Pordes, Marc Paterno, Jim Kowalkowski, Wes Ketchum, Laura Fields, Lynn Garren, Tom Junk, Tingjun Wang, Gianluca Petrillo

Remote: Matt Bass, Saba Sehrish, Vito Di Benedetto, (?)

 

There is no formal agenda of the meeting, round-table discussion only

 

Lynn Garren reported the build times of LArSoft code (i.e. building code from all the lar repositories)

  • In August, complete build of larsoft on GPVM took 36 min
    • Yesterday it was 68 min, and it took 65 min when products are from CVMFS
    • Building on woof takes  7 min instead of 4.5 min over the same time period
    • The load on the machines was unknown when these builds were run
    • Change in the time from Aug to date means there is issue in our code (assuming loading was similar)
  • Will send around a link pointing to information and results when completed.
  • There is a meeting tomorrow to discuss the build performance project
    • Jim Amundson is leading that. He  should be able to report weekly on status / progress
  • Meeting with Glenn Cooper this week (Jim Amundson and Lynn Garren)
    • the build numbers will be presented
    • Marc noted that people there was success in setting up machines for the art / LArSoft course that allowed people to build quickly. They know what is needed to do be able to do this.
  • Wes:  two issues - The platform and the build code. Lynn believes at least some of the problems and changes needed are in the code

 

  • Gianluca will begin usability project on Jan 20, at close of architecture project.

 

Lynn Garren reported on LArSoft Releases 

  • There will be a release candidate rc2 because dunetpc was not working with the tests
    • dunetpc now tests successfully
  • There will be a regular release this week
    • Matt Bass has code to discard particles
      • The mentioned code is in larcore and larsim
        • there are two corresponding feature branches that need to be added in conjunction
        • This code is needed for uboone production
      • An official request from uboone is needed, Matt Bass will request through redmine (Herb and Wes can review and add).
        • Tickets will be opened

 

Erica gave an update on LArSoft workshop and art/LArSoft course plans for this year

  • There will a 1-day LArSoft workshop in June to discuss the usability issues 
  • It will be coupled to the FIFE 2-day workshop, as it was last year
  • There will be no art/LArSoft this year due to budget constraints
  • The LArSoft (and art) material needs to be updated and expanded, but no effort for this
  • If the class is a priority for the experiments, then need to bring this situation to the attention of experiment management

 

Gianluca gave an update on Architecture project status

  • Architecture review closing by Jan 20
    • Track3DKalmanHit is last target for Saba
  • Corey is porting new version of Shower3D from LArLite
    • Some time since last port (March 2015). Significant changes since then
    • The work has not been coordinated with the integration project
    • Timelines:  week or two weeks GP thinks
      • Have issue tracking, but no time estimate is noted
    • ES:  Critical to understand what is involved in “porting”. Make sure that the integration project is addressing the right issues.
    • RP:  uboone needs to be present at the integration project meeting on Monday’s.
      • Corey should also consider whether he needs to be at the architecture meeting
      • Need to get uB effort involved in the integration project. Has not really contributed promised work yet.

 

CI test suite status

  • New test suite is in production since just before Chirstmas
    • the feature branch that was doing regression test was merged in the develop branch
  • First commits went well.
  • One issue from last coordination meeting
    • Mac OS reference data file reference problem
      • not the same as the linux reference file
      • Managed to create an appropriate reference file, so this part of the problem is resolve. Still do not understand why
      • Starting to work on this
  • Recent issue:  uboone reco stage 1 is failing. The results appear not to be reproducible. Believe there is a random number in there.
    • Issue on MacOS build service only (??)

 

libwda

  • Brandon Eberly noted a problem with libwda. Do we need this for uboone production?
    • Follow up with him to see what is going on here.

 

Mac OS support for El Capitan (Marc Paterno)

  • A major problem
    • LD_LIBRARY_PATH critical assumption for CET build system
    • Apple always discouraged use of Mac OS equivalent, DYLD_LIBRARY_PATH
    • New OS version does not inherit this equivalent, so it (i.e., DYLD_LIBRARY_PATH) cannot be set at a high level in the build configuration. 
    • An Apple security feature. There is a work around, but this turns off the security feature. MP does not believe this is a reasonable thing to ask people to do.
    • Ruth:  believes this falls under usability issues, so Jim A. He is already taking a survey via liaisons to find out what OS’s are in use
      • We need a statement to art community
    • Noted we do not build in the way that Apple has long recommended. The Linux world is different. Apple now does not use environment variables to find libraries.
      • This greatly increases the pain of supporting both Linux and Mac OS.
    • Send email to LArSoft noting this, stating that MP will send more information.

 

LArSoft implementation plan (Ruth Pordes)

  • LArSoft implementation plan.
  • Met with Matt Toups about efficiency goals in short term
    • Believe we need the real goals for this
    • Need a way to validate that we have met requirements
    • Noted that ES wants to go through capabilities, but we need to tie this to an end-to-end analysis. That is a lot of work
  • Bottom line: do not know how to do the implementation plan
  • Need regular reports from ES on integration of wire-cell and Pandora, and Ruth for FLUKA