Software – Matt should have it – need to see it on Matt’s PC
Horst responded that they are not interested in hosting/owning the system
PPD may be interested to host the system: Mike Roman
Clean room options
Why not the NWA?
James strongly advocates using A0
What needs to be done at A0?
Should meet with Dave Augustine to determine the scope
We have to own the place – no support from AD
Readiness for the FSP procurement
What is still missing?
Vessel
Holding for a final diameter of the FT from the ES simulations
Retaining plate – holding for the clocking pin – GDT – minor
Stand offs – revisit based on the electric field
Suspension of the frame: Matt wants to redo the FEA – wrong boundary conditions, need to figure out how to do it right (Brian’s question from the review)
Need to look at how to mount the clearing electrodes
Chris Jensen: look at g-2 design (Volodya Tyschenko, BNL)
Matt plan:
Foil assembly
Checking lengths of foils and springs
Measured STD on the spring constant to be 0.02 lbf/in, nominal is 0.89lbf/in
Fixture to comply with +- 0.077 length tolerance
Manufacturer’s limit on the spring tension before plastic deformation ???
Check Pin spacing for the springs
E-field simulations for the CE on the frame
Structural FEA on the frame
E-field simulation with frame, cathode and flanges
E-field on the stand-offs
E-field on the Feedthrough
Matt’s availability on this is more than 50%
There are minutes attached to this event.
Show them.