DUNE Project Management Meeting 5/22/2017 ----------------------------------------- Zoom: 534-572-111# dune-pm Present: Flavio, Dario, Ami, Jolie, Eric, Steve, Ed, Terri, Jack, Penka Schedule/Milestone Status (Penka) Updated Dual Phase schedule is in hand. May status request will be sent out this week. ProtoDUNE-SP Construction: (Flavio for Gina) PSL is focused on installing/extracting APA from shipping box. Flavio will visit PSL tomorrow. Kevin has sent out the APA PRR report. FNAL bars and CE reports almost ready. ProtoDUNE-SP Onsite: (Flavio) No missing elements, just need more people working onsite. Flavio is collecting a list of work items that need help and will distribute it soon. Some discussion of recruitment - email to collaboration? Spokes? Terri reported on a problem with the transformers that arrived at CERN (110V output instead of 220V) - a mitigation plan is in hand, with new transformers to be shipped by the end of June. We are waiting on Flavio for the protoDUNE-SP onsite part of the monthly report - he plans to complete it within a day or so. Dual-phase: (Dario) 3x1x1 filled with LAr. Heat input is high, with substantial boiling. Cold spots on outside are visible, but have not increased. Need to keep the steel above -60 C - so they will be monitored. Meeting with Marzio soon. Meeting with Elaine about interface between Dual Phase and Mezzanine at Far Site reveals no problems. FC module #0 for 6x6x6 looks good and production is approved by collaboration. FD Report: (Jack) Several discussions last week on FS interfaces. Marzio provided a summary on feedthrus and wants a list of missing items. Protego can mount a manifold on inside of cryostat, so specification of the manifold is needed. Various discussions on SP APA cabling continue. Other: Reviews: Some discussion of future SP design reviews has started. DP FC PRR Wednesday (May 24) at UTA. LBNC: Jimmy Proudfoot wants updates on APA schedule, DSS design and Photon system in the management session. Mike Lindgren wants discussion of far site logistics and cryostat roof penetrations in LBNF/DUNE interface session. No contact from Jocelyn on ProtoDUNE-DP session. We do not know if Kevin has contacted Gina about the ProtoDUNE-SP session. No meeting next week due to Memorial Day holiday. Next meeting is 5 June, 8am CDT Meeting ended at 8:28 CDT