AD Weekly Friday - 2017 Scheduling Meeting/Weekly Summary

US/Central
One West (Wilson Hall)

One West

Wilson Hall

Description
Weekly Scheduling, Planning and Status 
Performance Plots
Meetings will be held on Monday, Wednesday, and Friday of each week.
AD Weekly Friday - 2017 Scheduling Meeting/Weekly Summary (23 Jun 2017)

Linac

  • Running well.
Booster
  • Running well but down 1 RF station.
  • Would like to change the modulator on station 9 today to have it for the weekend.
  • Laser Notcher/Cogging studies were done yesterday. Plan to do more this afternoon.
  • Next week request some end of run studies.
  • Next Tuesday plan to work on RF station 21 during the maintenance period.
Main Injector & Recycler
  • RUnning well.
  • Last Friday made an access to fix RF stations 4 and 10 and do a rad survey. Turn-on was delayed by problems with MI60 VCB.
  • Accessed on Sunday to fix RRRF2 and investigate a problem with BLM high voltage in MI10 region.
  • Would like to access next Tuesday to repair the BLM HV problem. Also have a PS transductor study planned during that maintenance period.
NuMI
  • Running normally. Did a successful target scan on Wednesday.
  • Still have an LCW leak, now ~160 gal/day. Hope to address this on Tuesday.
NuMI Experiments
  • Running well.
Booster Neutrino
  • Running well. Target scans went well.
BNB Experiments
  • Running well.
Muon Rings
  • Busy week.
  • Loss studies.
  • Accessed to make quad moves.
  • Installed NMR probe.
  • Studying orbits in Delivery ring.
  • Sending beam to MC-1 on Owl shifts.
Muon Experiments
  • Had a cryo issue on Wednesday that was recovered.
  • Taking beam on owl shifts.
MTA
  • Cavity has been reinstalled.
SY120, Neutrino Muon, Meson Test, Meson Center
  • Running well.
  • EE support will investigate noisy MT4WL readback.
SY120 Experiments
  • Mtest is running fine.
  • Plan to do beam studies next week.
  • Hope to fill LAriat cryostat today.
  • SeaQuest is running fine.
FAST
  • Investigating flow restriction on Q480 magnet.
  • Would like to do power testing of D600 & 604 dipoles today.
  • 50MeV line elements have been tested.
  • Experiment X115 has been certified and will be installed next week.
  • CC1 &2 RF stations are pulsing.
Alignment
  • Supported FAST/IOTA & Mu2E.
ESH&Q
  • F sector chipmunk is due for cal this month. Will address it on Tuesday.
EE Support
  • V710 power supply wasn't following reference and found a contactor that wasn't closing properly.
  • Plan to investigate MI30L VCB on Tuesday.
Mechanical & Fluids
  • Made up water for LRF5 skid the past three days.
  • Making up water for the MI62 system due to the leak in the tunnel.
RF
  • Requesting 15 minutes today to diagnose BRF9.
FESS
  • Performing annual valve exercising.
  • Chlorination of MINOS sump seems to be working well.
  • F3 pond pump motor shows high vibration and it will likely need to be replaced.
  • Testing Andy's Pond system (provides water to CMTF) because it tripped last night.
  • Meeting with ComEd to inspect lines over Butterfield Road to make sure the delivery of the new detector can be accommodated.
Miscellaneous
  • We are planning a short maintenance period for next Tuesday morning. Beam off at 0600 and we expect ~6 hours down. Worklist is open.
There are minutes attached to this event. Show them.
    • 1
      Crew Chief One West

      One West

      Wilson Hall

      Slides
    • 2
      Operations Coordinator One West

      One West

      Wilson Hall

    • 3
      Linac One West

      One West

      Wilson Hall

      Running well.
    • 4
      Booster One West

      One West

      Wilson Hall

      Slides
      Running well but down 1 RF station.
      Would like to change the modulator on station 9 today to have it for the weekend.
      Laser Notcher/Cogging studies were done yesterday. Plan to do more this afternoon.
      Next week request some end of run studies.
      Next Tuesday plan to work on RF station 21 during the maintenance period.

    • 5
      Main Injector & Recycler One West

      One West

      Wilson Hall

      Slides
      RUnning well.
      Last Friday made an access to fix RF stations 4 and 10 and do a rad survey. Turn-on was delayed by problems with MI60 VCB.
      Accessed on Sunday to fix RRRF2 and investigate a problem with BLM high voltage in MI10 region.
      Would like to access next Tuesday to repair the BLM HV problem. Also have a PS transductor study planned during that maintenance period.
    • 6
      NuMI One West

      One West

      Wilson Hall

      Running normally. Did a successful target scan on Wednesday.
      Still have an LCW leak, now ~160 gal/day.  Hope to address this on Tuesday.
    • 7
      NuMI Experiments One West

      One West

      Wilson Hall

      Running well.
    • 8
      Booster Neutrino One West

      One West

      Wilson Hall

      Running well. Target scans went well.
    • 9
      BNB Experiments One West

      One West

      Wilson Hall

      Running well.
    • 10
      Muon Rings One West

      One West

      Wilson Hall

      Busy week.
      Loss studies.
      Accessed to make quad moves.
      Installed NMR probe.
      Studying orbits in Delivery ring.
      Sending beam to MC-1 on Owl shifts.
    • 11
      Muon Experiments One West

      One West

      Wilson Hall

      Speakers: Brendan Casey (FNAL), Brendan Kiburg (Fermilab), Joe Grange (Argonne National Lab)
      Had a cryo issue on Wednesday that was recovered.
      Taking beam on owl shifts.
    • 12
      MTA One West

      One West

      Wilson Hall

      Cavity has been reinstalled.
    • 13
      SY120, Neutrino Muon, Meson Test, Meson Center One West

      One West

      Wilson Hall

      Running well.
      EE support will investigate noisy MT4WL readback.
    • 14
      SY120 Experiments One West

      One West

      Wilson Hall

      Mtest is running fine.
      Plan to do beam studies next week.
      Hope to fill LAriat cryostat today.
      SeaQuest is running fine.
    • 15
      FAST One West

      One West

      Wilson Hall

      Investigating flow restriction on Q480 magnet.
      Would like to do power testing of D600 & 604 dipoles today.
      50MeV line elements have been tested.
      Experiment X115 has been certified and will be installed next week.
      CC1 &2 RF stations are pulsing.
    • 16
      PIP-II Injector Test One West

      One West

      Wilson Hall

    • 17
      Alignment One West

      One West

      Wilson Hall

      Supported FAST/IOTA & Mu2E.
    • 18
      Controls One West

      One West

      Wilson Hall

    • 19
      Cryo One West

      One West

      Wilson Hall

    • 20
      ESH&Q One West

      One West

      Wilson Hall

      F sector chipmunk is due for cal this month. Will address it on Tuesday.
    • 21
      EE Support One West

      One West

      Wilson Hall

      V710 power supply wasn't following reference and found a contactor that wasn't closing properly.
      Plan to investigate MI30L VCB on Tuesday.
    • 22
      Instrumentation One West

      One West

      Wilson Hall

    • 23
      Mechanical & Fluids One West

      One West

      Wilson Hall

      Made up water for LRF5 skid the past three days.
      Making up water for the MI62 system due to the leak in the tunnel.
    • 24
      RF One West

      One West

      Wilson Hall

      Requesting 15 minutes today to diagnose BRF9.
    • 25
      FESS One West

      One West

      Wilson Hall

      Speakers: Gilbert, Shirley, Sprosty
      Performing annual valve exercising.
      Chlorination of MINOS sump seems to be working well.
      F3 pond pump motor shows high vibration and it will likely need to be replaced.
      Testing Andy's Pond system (provides water to CMTF) because it tripped last night.
      Meeting with ComEd to inspect lines over Butterfield Road to make sure the delivery of the new detector can be accommodated.
    • 26
      Summer Shutdown 2017 One West

      One West

      Wilson Hall

      Speaker: Mr Cons Gattuso (Fermi Lab)
    • 27
      Miscellaneous One West

      One West

      Wilson Hall

      Slides
      We are planning a short maintenance period for next Tuesday morning. Beam off at 0600 and we expect ~6 hours down. Worklist is open.