Weekly Scheduling, Planning and Status
Performance Plots
Meetings will be held on Monday, Wednesday, and Friday of each week.
AD Weekly Friday - 2018 Scheduling Meeting/Weekly Summary (02 Mar 2018)
Crew Chief→ see slide
Operations Coordinator→ Performance Plots
Linac→ See Slides
Booster→ see Slides. Studies request on $17 & $19 cycles.
Main Injector & Recycler→ See Slides. Pending shutdown later this month for kicker flourinert investigation/kicker removal.
NuMI→ First RAD trip understood, only one of two kickers fired. Second RAD trip *MAY* have been RF related.
NuMI Experiments→ Running well. Still some residual issues from last Sunday's power glitch.
Booster Neutrino→ Running well.
BNB Experiments→ LArIAT sump pit issue.
Muon Rings→ Optics study on Wednesday. Yesterday turned on beam line to experiment. Will look at bunch shape this morning.
Muon Experiments→ Tuesday & Wednesday made measurement of the absolute calibration probe with manet on. Pumping down since Tuesday. Started bring quads up on Wednesday. 85% of nominal @ 17Kv. No difference in spark rate in repaired quad vs. other quads.
SY120, Neutrino Muon, Meson Test, Meson Center→ Good week delivering beam to Mtest users. Ops has done a good job in responding to their requests. Monday Meson open. Tuesday & Thursday open in morning. Access into SY F1 & F2 on Monday. Confirmed beam to Mcenter. Collimator question; needing to be open more for rates. ORC's on Monday
SY120 Experiments→ See SY minutes.
FAST/IOTA→ IOTA water manifold installation continues. Skew quads have been terminated in the Cave and their power supplies are nearly complete. Field testing should begin in 2 weeks. The nonlinear insert is being prepped for a stretched wire test to locate the magnetic center of each element to within ±50 µm. TD and Alignment Group are performing the measurements and referencing the magnet. Assembly of the lambertson magnet has begun. Assembly of the octupole string should begin within the next 2 weeks.
PIP-II Injector Test→ no report
Alignment→ nothing to report
Controls→ nothing to report
Cryo→ RED compresser tripped yesterday on high discharge temperature. Ongoing issue. Brown compressor started and in recovery mode. CMTF frig cold. G-2 running well, new dry expander. NML warm, expander overhaul. HAB warm.
ESH&Q→ nothing to report
EE Support→ nothing to report
Instrumentation→ "I have nothing to report!"
Mechanical & Fluids→ Access into F1 enclosure on Monday. MS2 half barrel glycol water added. ArCO2 bottles changed.
RF→ Running well. Module to tighten RF gap tolerance.
FESS→ Site #39 xformer failure. No new, found one at rail head. (it faulted) Found another one holding so far. Flooding various areas. Linac ejector pump issue, bad check valve.
Summer Shutdown 2018→ See slides. New Electronic Worklist entry.
Miscellaneous→ Shutdown/access week of March 27th. Congrates to Sergei, welcome Mike Lindgren as division head.
MTA→ no report
IOTA water manifold installation continues.
Skew quads have been terminated in the Cave and their power supplies are nearly complete. Field testing should begin in 2 weeks. The nonlinear insert is being prepped for a stretched wire test to locate the magnetic center of each element to within ±50 µm. TD and Alignment Group are performing the measurements and referencing the magnet. Assembly of the lambertson magnet has begun. Assembly of the octupole string should begin within the next 2 weeks.