Accelerator Scheduling Meeting

9 AM Meeting (07 Mar 2018)

Crew Chief Operations Summary→ See slide

Linac→ Marx code upgrade on LRF1&3. Debuncher pump issue, will swap to spare when repaired. (no operational impact) Thanks to MSD & fluids for working on pump. (no spare pump while repair in progress) RFQ tuning range was adjusted. Linac came back a bit lossy but continues to improve.

Booster→ Runnig 93% eff. Working on eff. Next Monday & Tuesday lattice measurement in association with Japanese Colaboration. 4 hrs of machine studies each day with $17 & $12 events in timeline. (est. 7-8% impact on BNB operation)

Booster Neutrino→ Running well. Thanks for horn PS work oppertunity.

BNB Experiments→ Running well.

Main Injector & Recycler→ Running well. As mention MI20 LCW work in progress. Studies planned in conjunction with Japanese Colaboration; parasitic with a $20 in timeline.

NuMI→ {had trouble hearing the report.}

NuMI Experiments→ All OK.

Muon Rings→ G-2 on access since Monday. Lattice studies for beamline. Maintenace on P1 & P2 PS's regulator cards. Access yesterday, concerns about water in AP50 pit; ctrl issue now OK. Some tunnel work. Repaired scrapers that had motion ctrl issues. Try to establish beam later today.

Muon Experiments→ Been in since Monday. Vacuum system opened. Found some independent problems. Will finish vacuum work later today. Would like to run the ring tonight. Tomorrow open during the day.

SY120→ Measurements made for P1&2 PS reg changes have helped to return to exact running values. MT4W work last night. Ops did some non-standard tuning to satisfy user requests. More EDIT controlled accesses today.

SY120 Experiments→ EDIT prime user during the day. Installed 1429 equipment.

ES&H→ Need to place badges in NuMI RAW room. (plan during shutdown later this month)

EE Support→ QF12, Q709, Q707 reg changes. Also MC5D. LRF3 resistor installed 1&3 Marx code upgrade, BNB horn reg swaped. KPS1c work. MT4W external regulator.

Mechanical→ Debuncher skip flexible connector issue. Small dripper on shaft of pump. Temperature issue MI20 LCW. Suspect a potentiometer on 3-way valve. Work in progress. DI bottles pending installduring 3/27 shutdown.

RF→ Some PM & calibrations during yesterday's DT. MIRF gap envelope threshold adjusted.

Controls→ PIOX cable swap seems to have solved the 377 timer issue.

Instrumentation→ Nothing to add.

FESS→ Divers in today for zebra mussels. Relamp in Klystron area. 10 ton air handler, 2 seed motor obsolete will use single speed motor. Andy's pump issue.

Miscellaneous→ Some mention about S:HP3DS (US?) ramp time early trigger.

 

There are minutes attached to this event. Show them.
    • 09:00 09:01
      Crew Chief Operations Summary 1m
      Slides

      See slide

    • 09:01 09:02
      Linac 1m

      Marx code upgrade on LRF1&3.  Debuncher pump issue, will swap to spare when repaired. (no operational impact) Thanks to MSD & fluids for working on pump. (no spare pump while repair in progress)  RFQ tuning range was adjusted.  Linac came back a bit lossy but continues to improve.

    • 09:02 09:03
      Booster 1m

      Runnig 93% eff. Working on eff. Next Monday & Tuesday lattice measurement in association with Japanese Colaboration.  4 hrs of machine studies each day with $17 & $12 events in timeline.  (est. 7-8% impact on BNB operation)

    • 09:03 09:04
      Booster Neutrino 1m

      Running well. Thanks for horn PS work oppertunity.

    • 09:04 09:13
      BNB Experiments 9m

      Running well.

       

    • 09:13 09:18
      Main Injector & Recycler 5m

      Running well.  As mention MI20 LCW work in progress. Studies planned in conjunction with Japanese Colaboration; parasitic with a $20 in timeline.

    • 09:18 09:19
      NuMI 1m

      {had trouble hearing the report.}

    • 09:19 09:20
      NuMI Experiments 1m

      All OK.

    • 09:20 09:21
      Muon Rings 1m

      G-2 on access since Monday. Lattice studies for beamline. Maintenace on P1 & P2 PS's regulator cards.  Access yesterday, concerns about water in AP50 pit; ctrl issue now OK.  Some tunnel work. Repaired scrapers that had motion ctrl issues. Try to establish beam later today.

    • 09:21 09:22
      Muon Experiments 1m

      Been in since Monday.  Vacuum system opened. Found some independent problems. Will finish vacuum work later today.  Would like to run the ring tonight. Tomorrow open during the day.

    • 09:22 09:23
      SY120 1m

      Measurements made for P1&2 PS reg changes have helped to return to exact running values.   MT4W work last night.  Ops did some non-standard tuning to satisfy user requests. More EDIT controlled accesses today.

    • 09:23 09:24
      SY120 Experiments 1m

      EDIT prime user during the day. Installed 1429 equipment.

    • 09:25 09:26
      ES&H 1m

      Need to place badges in NuMI RAW room. (plan during shutdown later this month)

    • 09:27 09:28
      EE Support 1m

      QF12, Q709, Q707 reg changes.  Also MC5D. LRF3 resistor installed 1&3 Marx code upgrade, BNB horn reg swaped.  KPS1c work. MT4W external regulator.

    • 09:28 09:29
      Mechanical 1m

      Debuncher skip flexible connector issue. Small dripper on shaft of pump. Temperature issue MI20 LCW. Suspect a potentiometer on 3-way valve.  Work in progress.  DI bottles pending installduring 3/27 shutdown.

    • 09:29 09:30
      Fluids 1m
    • 09:30 09:31
      RF 1m

      Some PM & calibrations during yesterday's DT.  MIRF gap envelope threshold adjusted.

    • 09:32 09:33
      Controls 1m

      PIOX cable swap seems to have solved the 377 timer issue.

    • 09:33 09:34
      Instrumentation 1m

      Nothing to add.

    • 09:34 09:35
      FESS 1m

      Divers in today for zebra mussels.  Relamp in Klystron area.  10 ton air handler, 2 seed motor obsolete will use single speed motor. Andy's pump issue.

    • 09:36 09:37
      Miscellaneous 1m

      Some mention about S:HP3DS (US?) ramp time early trigger.

    • 09:55 09:56
      MTA 1m