Dry Run for DOE IPR of the PIP-II Project at Fermilab

US/Central
Floating Point (Fermilab)

Floating Point

Fermilab

  • Thursday, 15 November
    • 08:00 08:50
      Project Management and CD-2/3a Preparation 50m
      Speaker: Marc Kaducak (Fermilab)
      Slides
    • 08:50 09:50
      Technical Integration 1h
      Speaker: Arkadiy Klebaner (Fermilab)
      Slides
    • 09:50 10:05
      Break 15m
    • 10:05 10:55
      Accelerator Systems 50m
      Speaker: Paul Derwent (Fermilab)
      Slides
    • 10:55 11:45
      SRF and Cryogenics 50m
      Speaker: Dr Genfa Wu (FNAL/TD)
      Slides
    • 11:45 12:45
      Lunch 1h
    • 12:45 13:35
      Accelerator Complex Upgrades 50m
      Speaker: Dr Ioanis Kourbanis (Fermilab)
      Slides
    • 13:35 14:35
      PIP-II Overview and International Context 1h
      Speaker: Dr Lia Merminga (FNAL)
      Slides
    • 14:20 16:30
      SC1 - Accelerator Systems Breakout Sessions
      • 14:20
        Accelerator Systems Overview (updates since CD-1, international partner activities, risks) 40m
        Speaker: Paul Derwent (Fermilab)
      • 15:00
        Beam Dynamics 30m
        Speaker: Dr Arun Saini (Fermilab)
      • 15:30
        High Power RF and RF Distribution 30m
        Speaker: Mr James Steimel (Fermilab)
        Slides
      • 16:00
        Low Level RF 25m
        Speaker: Mr Brian Chase (FNAL)
    • 14:20 16:30
      SC2 - Accel. Upgrades, Linac I&C Breakout Session
      • 14:20
        Linac Installation and Commissioning (updates since CD-1, risks) 15m
        Speaker: Fernanda Gallinucci Garcia (Fermilab)
        Slides
      • 14:35
        Warm Front End 30m
        Speaker: Lionel Prost (Fermilab)
        Slides
      • 15:05
        Test Infrastructure 30m
        Speaker: Mr Jerry Leibfritz (Fermilab)
        Slides
      • 15:35
        Building Infrastructure 20m
        Speaker: Mr Jonathan Hunt (Fermilab)
        Slides
      • 15:55
        Linac Installation 30m
        Speaker: Mr Curtis Baffes (Fermilab)
        Slides
    • 14:20 17:25
      SC3 - SRF and Cryogenics Breakout Session
      • 14:20
        SRF and Cryogenics Overview (updates since CD-1, international partner activities, risks, lessons learned e.g. transportation) 45m
        Speaker: Dr Genfa Wu (FNAL/TD)
        Slides
      • 15:05
        HWR 20m
        Speaker: Joe Ozelis (Fermilab)
        Slides
      • 15:25
        SSR1, SSR2 40m
        Speaker: Donato Passarelli (Fermilab)
      • 16:05
        LB650, HB650 40m
        Speaker: Dr Saravan Chandrasekaran (FNAL/TD)
        Slides
    • 14:20 16:30
      SC4 - Conventional Facilities Breakout Session
      • 14:20
        CF Overview 45m
        Speaker: Steven Dixon (Fermi National Accelerator Laboratory)
        Slides
      • 15:05
        Site Preparation 45m
        Speaker: Randal Wielgos (Fermilab)
        Slides
      • 15:50
        Interfaces with other projects 30m
        Speaker: Randal Wielgos (Fermilab)
        Slides
    • 14:20 16:30
      SC5/6/7 - Management, Cost/Schedule and ESH&Q Breakout Session
      • 14:20
        International Governance and Agreement Status 1h
        Speaker: Dr Lia Merminga (FNAL)
      • 15:20
        Resource Loaded Schedule Status 30m
        Speaker: Dr Luisella Lari (Fermilab)
      • 15:50
        CD-2/3a Preparation Status 30m
        Speaker: Marc Kaducak (Fermilab)
        Slides
    • 14:35 14:50
      Break 15m
    • 14:50 15:30
      Linac Installation and Commissioning 40m
      Speaker: Fernanda Gallinucci Garcia (Fermilab)
      Slides
    • 15:30 16:10
      Conventional Facilities 40m
      Speaker: Steven Dixon (Fermi National Accelerator Laboratory)
      Slides
  • Friday, 16 November
    • 08:00 08:40
      Incorporating Lessons Learned 40m
      Speaker: Ms Jemila Adetunji (FNAL)
      Slides
    • 08:00 09:30
      SC1 - Accelerator Systems Breakout Session
      • 08:00
        Magnets and Power Supplies 30m
        Speaker: Mr Bruce Hanna (Fermi National Accelerator Lab)
        Slides
      • 08:30
        Instrumentation 30m
        Speaker: Vic Scarpine (Fermilab)
        Slides
      • 09:00
        Controls 30m
        Speaker: James Patrick (Fermilab)
        Slides
    • 08:00 10:15
      SC2 - Accel. Upgrades, Linac I&C Breakout Session
      • 08:00
        Beam Commissioning 20m
        Speaker: Fernanda Gallinucci Garcia (Fermilab)
        Slides
      • 08:20
        Accelerator Complex Upgrades Overview (updates since CD-1, risks) 10m
        Speaker: Dr Ioanis Kourbanis (Fermilab)
      • 08:30
        Booster 30m
        Speaker: David Johnson (Fermilab)
        Slides
      • 09:00
        Main Injector, Recycler 30m
        Speaker: Mr Joseph Dey (Fermialb)
      • 09:45
        Transfer Line, Beam Absorber 30m
        Speaker: Dr Meiqin Xiao (AD/RR)
        Slides
    • 08:00 09:30
      SC3/4 - Joint Breakout Session on CD-3a Scope
      • 08:00
        Cryoplant Requirements and Design 30m
        Speaker: Benjamin Hansen
        Slides
      • 08:30
        Cryoplant Building and Site Prep Final Design Plan 1h
        Speaker: Steven Dixon (Fermi National Accelerator Laboratory)
        Slides
    • 08:00 09:30
      SC5/6/7 - Management, Cost/Schedule, and ESH&Q Breakout Session
      • 08:00
        ES&H 30m
        Speaker: John Anderson Jr. (ESH&Q Section Radiation Physics Engineering)
        Slides
      • 08:30
        Top Project Risks 30m
        Speaker: Marc Kaducak (Fermilab)
      • 09:00
        Quality Assurance 30m
        Speaker: Ms Jemila Adetunji (FNAL)
    • 08:40 09:40
      Cryoplant Requirements and Design 1h
      Speaker: Benjamin Hansen
    • 09:40 10:00
      Break 20m
    • 09:45 10:45
      SC3 - SRF and Cryogenics Breakout Session
      • 09:45
        Half Wave Resonator 30m
        Speaker: Zachary Conway (Argonne National Laboratory)
        Slides
      • 10:15
        Cryo Distribution System 30m
        Speaker: Mr Andrew Dalesandro (FNAL)
        Slides
    • 09:45 10:15
      SC4 - Conventional Facilities Breakout Session
      • 09:45
        Requirements Development 30m
        Speaker: Steven Dixon (Fermi National Accelerator Laboratory)
    • 10:00 11:00
      Cryoplant Building and Site Prep Final Design Plan 1h
      Speaker: Steven Dixon (Fermi National Accelerator Laboratory)
      Slides