- Discuss the staging of equipment on the cantilevered section of the mezzanine and the loads.
- Include sequencing of installation. Feed thru vent pipes, are the gas analyzers in this scope, where does all of this equipment go. This should include the physical items needed underground and at the surface, trades and services.
- Make a list of assumptions as to who is providing specific tooling (examples: shaft guides for items, loading and unloading conveyances at surface and 4850 (who designs?), special carts for dewars, rigging points to items with CG calculations) Using a table for these items, we can fill in the names during the meeting.
- Who is designing the stands on the mezzanine for the dewars and tanks shown in the model?
- Who is designing the pipe supports that attach to the wall? Need to inform SDSD for procurement and identify necessary resources for installation.