E4R Test Facility Review

chaired by Henryk Piekarz
Thursday, September 10, 2009 from to (US/Central)
at Fermilab ( One East )
Wilson Hall, first floor
Description
Internal review of E4R Test Facility
Material:
Go to day
  • Thursday, September 10, 2009
    • 09:00 - 09:30 Motivation, arrangement and goals of the HTS transmission line conductor test 30'
      Speaker: H. Piekarz
      Material: Paper pdf file Slides powerpoint file
    • 09:30 - 09:45 Magnet and power supply arrangement for the HTS conductor tests under a sweeping B-field 15'
      Speaker: S. Hays
      Material: Paper pdf file Slides powerpoint file
    • 09:45 - 10:00 Cryogenic system arrangement for the HTS conductor tests at E4R 15'
      Speaker: Y. Huang
      Material: Paper pdf file Slides powerpoint file