TSIB High Power Targetry Lab preliminary design review
Friday, 1 October 2021 -
10:00
Monday, 27 September 2021
Tuesday, 28 September 2021
Wednesday, 29 September 2021
Thursday, 30 September 2021
Friday, 1 October 2021
11:00
Opening Remarks and Project Overview
-
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
Andrew Federowicz
Opening Remarks and Project Overview
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
Andrew Federowicz
11:00 - 11:20
11:20
Recommendations from previous review
-
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
Recommendations from previous review
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
11:20 - 11:40
11:40
Update from previous review
-
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
Update from previous review
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
11:40 - 12:00
12:00
Break
Break
12:00 - 12:30
12:30
Safety, hazard and mitigation plan
-
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
Eric Schlatter
Safety, hazard and mitigation plan
Frederique Pellemoine
(Fermilab -AD - TSD - TRD)
Eric Schlatter
12:30 - 13:00
13:00
Design Progress
-
Keith Anderson
Design Progress
Keith Anderson
13:00 - 14:00
14:00
Discussion
Discussion
14:00 - 14:30
14:30
Break
Break
14:30 - 15:00
15:00
Executive Session
Executive Session
15:00 - 17:00