MAGIS-100 Installation Workshop

US/Central
    • 1
      Executive session

      Preparation by MAGIS-100 team.

    • 2
      Introduction

      Summarize main challenges and discuss basis for charge questions. Seeking feedback on equipment installation methods and personnel access.

      Speaker: Linda Valerio (Fermilab)
    • 3
      Guided discussion 1

      Installation option 1 – Vertical rail system

      Installation option 2 – Horizontal rail system used with main crane or mast climber

      Speakers: Arvydas Vasonis (fess), Mandy Kiburg (Fermilab), Noah Curfman, Ty Funk
    • 10:15
      Break
    • 4
      Guided discussion 2

      Installation option 3 – Secondary crane used with cameras and dagger system, including potential guiding systems

      Installation option 4 – Custom cantilevered fixture with main crane and remote disconnect

      Personnel Access options – Range of options for installation and maintenance

      Summary – Closing thoughts and suggestions for follow-up/closeout meeting

      Speakers: Arvydas Vasonis (fess), Linda Valerio (Fermilab), Martin Murphy (Fermilab AD Operations), Noah Curfman, Ty Funk