Membrane modules tests, installation,...
M0 discussion:
* 4 modules still outside
* M6 ready to install (new WLS and tested)
* M5 was tested but cracked WLS--> WLS to be replaced
Follow up: does the new spacer part not have enough tolerance to cope with the WLS size variations? Design to be revisited, presentation by Zach next week at the CM.
* M7 and M8 were tested back in April but with dimples --> WLS to be replaced
* 4 new WLS available in a box in the PDS room
* Zach and Jay arriving on 30/09. Can do ~1 module a day. Installation on the following week
* Testing (if possible) to be done end of 30/09 week, beginning of the following. Potentially all ok in the test stand and LAr available - need to notify Filippo.
*PMT installation by spanish team week of 14/10.