1.TMS studies: split the studies into several groups to be reviewed with the ND reco/sim group. The two review dates are December 11th and January 8th.
Expect the studies being done and documentation written out in detail.
Important points: how the studies were done, what are the results and interpretations. Qualities of the plots and suitable captions are important.
Going through the readiness of several studies: Kiyoung’s, Xiaoyan’s, Asa’s studies are ready to be reviewed in December. Kates's study on ND-LAR–TMS matching and Liam’s and Jeffrey’s study on the energy/momentum resolution will be reviewed in January.
2. Asa’s presentation: See more details in the slide.
Implementing a new geometry of TMS. Current geometry is from the CDR era.
Changes made: steel thickness, gaps between steel, scintillator bar dimensions.
Asa implemented the changes and ran the code, it passed all checks.
Next steps: run a tiny production to test the new geometry. With the PDR coming up, it's good to do it as soon as possible.