Desktop + Measure actuator x-vs-p on test hoop Lab-6 - Clean/service clean room - Test air quality - Move cavity into clnrm (with plastic pallet, etc.) - Remove vessel covers, cover seal surfaces for protection (extra O-rings?) - Install temporary cover plates on vessel? - Move vessel into clnrm - Move small crane into clean room - Move horizontal stand in clean room - Seal external doors near clean room - Clean clean room, parts, tools - Identify/handle waste management - Mount cavity on horizontal stand - Remove cavity cover plates - Clean cavity as needed - Survey tuner mounting rings - Install flat Cu endplates on cavity - Install tuner forks - Install thermocouples and readout? - Set up water supply - Pressure test water lines - Bend water lines - Remove vessel temporary cover plates - Assemble/move insertion fixture in clean room - Clean parts - Disassemble/remove horizontal stand - Mount cavity on vertical stand - Install RF pickups (tophat if available, probe adapters otherwise) - Measure cavity RF parameters (f, S11, S21, Q) [including effect of ports, etc.] - Install water feed through - Retest water lines - Swap in Be windows - Measure cavity RF parameters - Remove tophat - Remove Be windows - Install cavity in vessel - Remove vertical stand - Align/survey cavity in vessel - Install RF tophat - Install actuators - Set up air supply - Connect air, pressure control - Measure tuner xfer function - Install microphones? - Install other diagnostics - Install couplers (if available) - Measure cavity RF parameters - Adjust coupling, record/mark loop orientation - Remove couplers - Remove actuators - Replace Be windows with Al covers - Clean parts - Install temporary vessel covers - Disassemble small crane, move to MTA Fermilab machine/work shops - Machine tuner fork contact pads - Add mounting holes on forks? - Build (buy?) air manifold and brackets (Ryan) - Assemble air system - Build (buy) water hoses and brackets (Ryan) x Build temporary RF adapter plates (get from LBNL) LBNL machine shops - Build couplers Elsewhere RF7/LK8 - Set up interlocks - Set up control electronics - Set up control software - Test interlocks - Test amplitude control - Test breakdown triggers - Set up coupler conditioning software MTA - Disassemble small crane, remove from MTA - Move clean room over cavity - Remove Be windows - Move Be windows to Lab-6 - Rent large crane, move into MTA - Disconnect old cavity in MTA - Remove old cavity from platform - Remove old cavity from MTA (to warehouse?) x Assemble station 2 vacuum system x Set up readout for S2 vacuum system x Test station 2 vacuum system x Mount couplers on conditioning stand x Pumpdown leak-ck couplers x Connect couplers to RF at station 2 x Coupler high-power conditioning - Move vessel, covers, Be windows into MTA - Move small crane into MTA, assemble - Clean MTA clnrm - Remove temporary covers (in clean rm) - Swap in Be windows? - LLRF tests? - Install covers on vessel (in cleanrm) x Pumpdown leak-check - Rent large crane, move into MTA - Swap in operational stand - Lift vessel onto platform - Survey/align vessel - Raise clean room? - Move clean room over vessel - Install couplers - Install actuators - Measure/adjust coupling - Measure cavity RF parameters - Move clean room out - Connect vacuum system - Pumpdown leak-ck - Bake? - Install air system - Install compressed air tubing - Connect air - Connect tuner control - Measure tuner xfer function - Install water hoses - Connect water - Cavity/cable RF calibration - Connect coax - Connect, test instrumentation - Commission at B=0 - Disconnect, purge, move clean rm over module - Remove/inspect couplers - Remove vessel center plate, inspect cavity interior - Reinstall vessel center plate - Reinstall, adjust couplers - Cavity/cable RF calibration - Start operations - Cavity run at higher gradient (?) - Lather, rinse, repeat - Cavity run at B>0