Matt found a delay in W/Re foil delivery. The order has never been placed due to miscommunication between Deb and Cindy – different databases, no tracking mechanism on our side.
New order – 2 months lead time
Still have some available, will be able to start
Vendor still may have something in stock?
Salli will be back on 27th
Status of drawings:
Prototype in work
Frame is done
Baffle will be done today
Foils drawn with shims
Baffles: Matt and Mike propose to remove it. Need to make sure Dave is OK with that. Baffles serve multiple functions
Ask Masahito about 25%Re foils