Ran alright. Looked at LRF5 during the Maintenance period. LRF1 tripped, operations cound not reset, expert called in to reset.
Booster
Installed new RF cavity and leaked checked Long 18 and 22 during the maintenance period. Had to access Booster to open a manual vacuum avalve. BRF5 tripped, changed bad sola supply, back on line now.
Booster Neutrino
Check sensors on the RAW system and adjusted Neutrino timing once the New fiber cables were pulled.
BNB Experiments
Running well.
Main Injector & Recycler
Work continues on vacuum problem at MI-52.SEY measurements were taken during the maintenance period.
NuMI
PM in target hall and absorber RAW. Horn 1 RAW system is loosing water. PM on the Munter units. Worked on the A power supply for the horn.
NuMI Experiments
Running well. Fixed a few cards and changed Neutrino delays.
Muon Rings
Bend buss is back up. Aligned 2 injection quads. Working on the target vault SEM. Rotated a beam pipe for better transmission.
SY120
MS2 LCW cooling tower 1B is back on, we now have 5 working fans for MS2.
SY120 Experiments
SeaQuest is okay. Lariat will turn off tomorrow for an argon delivery. Exps. T1041 and T1315 are installed in MT6, sign offs are scheduled for 1100 today. 2 more experiments will be installed next week including 1 in M03.
ES&H
Waiting for F2 sump discharge to finish, still have a lock on MLAM.
EE Support
Worked on HV703 and the NUMI horn Apower supply during the maintenance period.
Mechanical
Worked on various jobs during the maintenance period including MI-52 vacuum leak.
Fluids
Worked on various air leaks in the MI, made up water in the Proton Source. Replaced an RTD at the MI-20 pump room
RF
Installed a Booster cavity. Changed out the PA for MIRF14.
MTA
Not running right now. Need to replace an OD head in the MTA hall.
Controls
Replaced the crushed fibers for the Neutrino experiments.
Instrumentation
Nothing to report.
FESS
Found another leak in the F2 Sump discharge line. Investigated the MI-52 sump discharge line with a camera. Performed PM on a Booster exhaust fan. Working on a CUB chilled water pump.
There are minutes attached to this event.
Show them.
09:00
→
09:01
Crew Chief Operations Summary1m
Slides
09:01
→
09:02
Linac1m
Ran alright. Looked at LRF5 during the Maintenance period. LRF1 tripped, operations cound not reset, expert called in to reset.
09:02
→
09:03
Booster1m
Installed new RF cavity and leaked checked Long 18 and 22 during the maintenance period. Had to access Booster to open a manual vacuum avalve. BRF5 tripped, changed bad sola supply, back on line now.
09:03
→
09:04
Booster Neutrino1m
Check sensors on the RAW system and adjusted Neutrino timing once the New fiber cables were pulled.
09:04
→
09:13
BNB Experiments9m
Running well.
09:13
→
09:18
Main Injector & Recycler5m
Work continues on vacuum problem at MI-52.SEY measurements were taken during the maintenance period.
09:18
→
09:19
NuMI1m
PM in target hall and absorber RAW. Horn 1 RAW system is loosing water. PM on the Munter units. Worked on the A power supply for the horn.
09:19
→
09:20
NuMI Experiments1m
Running well. Fixed a few cards and changed Neutrino delays.
09:20
→
09:21
Muon Rings1m
Bend buss is back up. Aligned 2 injection quads. Working on the target vault SEM. Rotated a beam pipe for better transmission.
09:21
→
09:22
SY1201m
MS2 LCW cooling tower 1B is back on, we now have 5 working fans for MS2.
09:22
→
09:23
SY120 Experiments1m
SeaQuest is okay. Lariat will turn off tomorrow for an argon delivery. Exps. T1041 and T1315 are installed in MT6, sign offs are scheduled for 1100 today. 2 more experiments will be installed next week including 1 in M03.
09:24
→
09:25
ES&H1m
Waiting for F2 sump discharge to finish, still have a lock on MLAM.
09:26
→
09:27
EE Support1m
Worked on HV703 and the NUMI horn Apower supply during the maintenance period.
09:27
→
09:28
Mechanical1m
Worked on various jobs during the maintenance period including MI-52 vacuum leak.
09:28
→
09:29
Fluids1m
Worked on various air leaks in the MI, made up water in the Proton Source. Replaced an RTD at the MI-20 pump room
09:29
→
09:30
RF1m
Installed a Booster cavity. Changed out the PA for MIRF14.
09:30
→
09:31
MTA1m
Not running right now. Need to replace an OD head in the MTA hall.
09:31
→
09:32
Controls1m
Replaced the crushed fibers for the Neutrino experiments.
09:32
→
09:33
Instrumentation1m
Nothing to report.
09:33
→
09:34
FESS1m
Found another leak in the F2 Sump discharge line. Investigated the MI-52 sump discharge line with a camera. Performed PM on a Booster exhaust fan. Working on a CUB chilled water pump.