9 AM Meeting

US/Central
Huddle

Huddle

Description
Mon-Thurs Accelerator Scheduling Meeting
9 AM Meeting (26 Apr 2017)

Linac

  • Ran alright. Looked at LRF5 during the Maintenance period. LRF1 tripped, operations cound not reset, expert called in to reset.
Booster
  • Installed new RF cavity and leaked checked Long 18 and 22 during the maintenance period. Had to access Booster to open a manual vacuum avalve. BRF5 tripped, changed bad sola supply, back on line now.
Booster Neutrino
  • Check sensors on the RAW system and adjusted Neutrino timing once the New fiber cables were pulled.
BNB Experiments
  • Running well.
Main Injector & Recycler
  • Work continues on vacuum problem at MI-52.SEY measurements were taken during the maintenance period.
NuMI
  • PM in target hall and absorber RAW. Horn 1 RAW system is loosing water. PM on the Munter units. Worked on the A power supply for the horn.
NuMI Experiments
  • Running well. Fixed a few cards and changed Neutrino delays.
Muon Rings
  • Bend buss is back up. Aligned 2 injection quads. Working on the target vault SEM. Rotated a beam pipe for better transmission.
SY120
  • MS2 LCW cooling tower 1B is back on, we now have 5 working fans for MS2.
SY120 Experiments
  • SeaQuest is okay. Lariat will turn off tomorrow for an argon delivery. Exps. T1041 and T1315 are installed in MT6, sign offs are scheduled for 1100 today. 2 more experiments will be installed next week including 1 in M03.
ES&H
  • Waiting for F2 sump discharge to finish, still have a lock on MLAM.
EE Support
  • Worked on HV703 and the NUMI horn Apower supply during the maintenance period.
Mechanical
  • Worked on various jobs during the maintenance period including MI-52 vacuum leak.
Fluids
  • Worked on various air leaks in the MI, made up water in the Proton Source. Replaced an RTD at the MI-20 pump room
RF
  • Installed a Booster cavity. Changed out the PA for MIRF14.
MTA
  • Not running right now. Need to replace an OD head in the MTA hall.
Controls
  • Replaced the crushed fibers for the Neutrino experiments.
Instrumentation
  • Nothing to report.
FESS
  • Found another leak in the F2 Sump discharge line. Investigated the MI-52 sump discharge line with a camera. Performed PM on a Booster exhaust fan. Working on a CUB chilled water pump.
There are minutes attached to this event. Show them.
    • 09:00 09:01
      Crew Chief Operations Summary 1m
      Slides
    • 09:01 09:02
      Linac 1m
      Ran alright. Looked at LRF5 during the Maintenance period. LRF1 tripped, operations cound not reset, expert called in to reset.
    • 09:02 09:03
      Booster 1m
      Installed new RF cavity and leaked checked Long 18 and 22 during the maintenance period. Had to access Booster to open a manual vacuum avalve. BRF5 tripped, changed bad sola supply, back on line now.
    • 09:03 09:04
      Booster Neutrino 1m
      Check sensors on the RAW system and adjusted Neutrino timing once the New fiber cables were pulled.
    • 09:04 09:13
      BNB Experiments 9m
      Running well.
    • 09:13 09:18
      Main Injector & Recycler 5m
      Work continues on vacuum problem at MI-52.SEY measurements were taken during the maintenance period.
    • 09:18 09:19
      NuMI 1m
      PM in target hall and absorber RAW. Horn 1 RAW system is loosing water. PM on the Munter units. Worked on the A power supply for the horn.
    • 09:19 09:20
      NuMI Experiments 1m
      Running well. Fixed a few cards and changed Neutrino delays.
    • 09:20 09:21
      Muon Rings 1m
      Bend buss is back up. Aligned 2 injection quads. Working on the target vault SEM. Rotated a beam pipe for better transmission.
    • 09:21 09:22
      SY120 1m
      MS2 LCW cooling tower 1B is back on, we now have 5 working fans for MS2.
    • 09:22 09:23
      SY120 Experiments 1m
      SeaQuest is okay. Lariat will turn off tomorrow for an argon delivery. Exps. T1041 and T1315 are installed in MT6, sign offs are scheduled for 1100 today. 2 more experiments will be installed next week including 1 in M03.
    • 09:24 09:25
      ES&H 1m
      Waiting for F2 sump discharge to finish, still have a lock on MLAM.
    • 09:26 09:27
      EE Support 1m
      Worked on HV703 and the NUMI horn Apower supply during the maintenance period.
    • 09:27 09:28
      Mechanical 1m
      Worked on various jobs during the maintenance period including MI-52 vacuum leak.
    • 09:28 09:29
      Fluids 1m
      Worked on various air leaks in the MI, made up water in the Proton Source. Replaced an RTD at the MI-20 pump room
    • 09:29 09:30
      RF 1m
      Installed a Booster cavity. Changed out the PA for MIRF14.
    • 09:30 09:31
      MTA 1m
      Not running right now. Need to replace an OD head in the MTA hall.
    • 09:31 09:32
      Controls 1m
      Replaced the crushed fibers for the Neutrino experiments.
    • 09:32 09:33
      Instrumentation 1m
      Nothing to report.
    • 09:33 09:34
      FESS 1m
      Found another leak in the F2 Sump discharge line.  Investigated the MI-52 sump discharge line with a camera. Performed PM on a Booster exhaust fan. Working on a CUB chilled water pump.
    • 09:35 09:36
      Miscellaneous 1m