PIP-II Architectural Advisory Board

US/Central
WH13SE - The Appearance (Fermilab- Wilson Hall)

WH13SE - The Appearance

Fermilab- Wilson Hall

Clayton Witt (Gensler), Steven Dixon (Fermi National Accelerator Laboratory)
Description

This is the Second Meeting of the PIP-II Architectural Advisory Board 

In the last few months the project team has begun to socialize the project within the Fermilab community by presenting in-progress status reports to both the Retired Scientist group in December and a Lab-wide audience during lunchtime presentation earlier this month. Both were well attended and generated a number of comments and suggestions.

The team has also made significant progress on the Site Preparation work for PIP-II and we have begun the design of the Cryogenics Plant Building. With the design progressing towards a 60% completion review at the end of March, this would be a good time to meet again and present the progress that has been made and get your thoughts on the design concepts for the Cryogenics Plant Building since it sets the stage for the remaining work.

Introduction
Slides
The agenda of this meeting is empty