Please read these instructions before posting any event on Fermilab Indico
Indico will be down for maintenance on August 8th from 6-7PM
Progress since last CT mtg :
Next two weeks :
Continued progress on unit and integration tests.
Have integration test working that runs a pacman-readout that uses 'larpix-control' package from ND-LAr to make fake data. Understand from Alessandro that it is not desired to include packages like this in the DAQ repo so looking for a way around including it (probably pre-generate data packets to be sent in test)
Looking to get hold of physical pacman hardware (meeting with SLAC group later) for testing. After testing is complete will focus on adding ND-LAr light and ND-GAr charge readout.
Progress
Intended work
Cross group
Progress
v1.1.2 deployed for cold box.
Next Steps
Cross-WG
Since last meeting:
Until next meeting
For further discussion