PIP-II MEBT Line FDR
Thursday 16 Mar 2023, 08:00
→
16:00
US/Central
Dark Side Conference Room (WH6NW)
Dark Side Conference Room (WH6NW)
Description
Review materials are archived in Teamcenter (TC# ED0023594)
Charge
Deliverables
6.2.01 - PIP-II Warm Front End FRS (ED0008004)
6.2.02 - PIP-II MEBT FRS (ED0001303)
6.2.03 - PIP-II MEBT TRS (ED0014432)
6.2.04 - PIP-II MEBT ISD (ED0022346)
6.3.01 - PIP-II MEBT line Prevention through Design table (PIP-II-doc-6457)
6.3.02 - PIP-II MEBT line Failure Mode and Effect Analysis (PIP-II-doc-6454)
6.4.07 - PIP-II MEBT Drawing Tree (BOM)
6.4.09 - PIP-II WFE lattice file (Excel) (ED0011224)
6.4.10 - Test results of PIP2IT MEBT vacuum protection system (NAPAC 2019)
6.5.01 - PIP-II MEBT QC Plan (ED0023472)
6.5.02 - PIP-II Warm Front End Installation Plan (draft) (ED0020527)
6.5.03 - Bunching cavities procurement specification (update) (ED0000731)
Drawings (Nx screenshots)
6.4.01 - Full MEBT (F10101511)
6.4.02 - PIP-II MEBT beam line Girder 1 (F10180723)
6.4.03 - PIP-II MEBT beam line Girder 2 (F10179867)
6.4.04 - PIP-II MEBT beam line Girder 3 (F10179000)
6.4.05 - PIP-II MEBT beam line Girder 4 (F10179772)
6.4.06 - PIP-II MEBT beam line Girder 5 (F10182245)
6.4.08 - PIP-II Lattice Files (CAD) (F10101501)
Project High Level Documents
6.1.01 - PIP-II Technical Review Plan (ED0008163)
6.1.02 - PIP-II QA Plan (PIP-II-doc-142)
6.1.03 - PIP-II Systems Engineering Management Plan (ED0008164)
6.1.04 - PIP-II IESH Management Plan (PIP-II-doc-141)
6.1.05 - PIP-II Value Engineering Plan (PIP-II-doc-2830)
6.1.06 - PIP-II Linac Installation and Commissioning System Design Plan (ED0010553)
6.1.08 - PIP-II Consolidated ICD Master (ED00010433)
6.1.09 - PIP2IT Commissioning Report (PIP-II-doc-5622)
08:00
→
08:20
Executive session
20m
Speakers
:
Consolato Gattuso
(Fermi Lab AD)
,
Jeffrey Eldred
(Fermilab)
,
Kevin Duel
08:20
→
08:30
Welcome and Logistics
10m
Speakers
:
Christopher Becker
(PIP-II Technical Integration)
,
Jeremiah Holzbauer
(Fermi National Accelerator Laboratory)
PIP-II Review Introduction for Reviewers.pptx
08:30
→
09:45
Introduction
1h 15m
Speaker
:
Lionel Prost
(Fermilab)
Introduction to PIP-II and its MEBT
09:45
→
10:30
MEBT beam line overview
45m
Speaker
:
Alexander Shemyakin
(Fermilab)
MEBT overview FDR.pdf
10:30
→
10:45
Break
15m
10:45
→
11:15
Transition from the PIP2IT MEBT to PIP-II's
30m
Speaker
:
Lionel Prost
(Fermilab)
PIP-II MEBT vs. PIP2IT MEBT
11:15
→
12:15
Beam line mechanical design
1h
Speaker
:
Jason Morin
(Fermilab)
MEBT FDR slides Mechanical Design.pptx
12:15
→
13:00
Lunch
45m
13:00
→
14:00
Wrap-up/Discussion
1h
14:00
→
15:30
Executive session
1h 30m
Closeout preparation
15:30
→
16:00
Closeout
30m
Speaker
:
Jeffrey Eldred
(Fermilab)