DAQ Coordination Meeting

America/Chicago
    • 09:00 09:05
      General news 5m
      Speakers: Alessandro Thea (STFC Rutherford Appleton Laboratory), Asher Kaboth (RHUL), Roland Sipos (CERN)
    • 09:05 09:20
      Actions from previous meetings 15m
      Speakers: Alessandro Thea (STFC Rutherford Appleton Laboratory), Asher Kaboth (RHUL), Roland Sipos (CERN), Wesley Ketchum (Fermi National Accelerator Laboratory)
    • 09:20 09:30
      Run Coordination news 10m
      Speaker: Wesley Ketchum (Fermi National Accelerator Laboratory)
    • 09:30 10:10
      Planning Workshop follow-up 40m
      Speakers: Alessandro Thea (STFC Rutherford Appleton Laboratory), Asher Kaboth (RHUL), Giovanna Lehmann (CERN), Roland Sipos (CERN), Wesley Ketchum (Fermi National Accelerator Laboratory)
    • 10:10 10:11
      Working groups round table 1m
      Speakers: Adam Barcock (UKRI STFC), Alec Habig (Univ. of Minnesota Duluth), Alexander Tapper (Imperial College London), Artur Sztuc (University College London), Bonnie King (FNAL), David Cussans (University of Bristol), Jonathan Hays (Queen Mary University of London), Joshua Klein, Kurt Biery (Fermilab), Pierre Lasorak (Imperial College London), Roland Sipos (CERN), Stoyan Trilov, Wesley Ketchum (Fermi National Accelerator Laboratory)
      CCM

      Timing

      • Preparations for NP04 running going OK.
        • List of timing endpoint addresses for readout/calibration units on NP04 complete except for SSP LED flashers.
        • Return path of devices except for SSPs tested and mostly OK
          • All WIBs need a firmware update to allow full access to timing endpoint registers via timing fibre from timing master
          • No (upstream) communication with some WIBs (middle in crate) - issue under investigation
        • Fanout 1 (NP04 master) locked to 10 MHz from accelerator
        • CRT timing unit commissioned
      • RFQ for DUNE-variant AFCs should go out this week
      • After delay due to last minute design change FIB design should be ready for quotes/manufacture this week.
      • In process of updating post-PRR schedule (concentrating on items that are also in US P6 schedule)
      • Initial integration of timing with OKS / 5.x complete. Tested in hardware to some extent. Code and schema being reviewed
      • Work in progress on allowing setup/control of periodic timing system messages via nanotimingrc

      Trigger

      • TPG & Trigger commissioning ongoing at NP04
      • TP rates we see: ~0.7MHz/plane, = 2MHz per APA
        • Unfortunately the readout applications currently cannot keep up with these TP rates.
        • Done CPU pinning optimization & added non-zero queue timeouts that allow us to run TPG on one plane at desired thresholds.
        • Proposed changes from Giovanna for the TP->Buffer->TPSet module to work on per-plane basis, resolving the issue.
        • This will have positive implications on the trigger: TA algorithms will work per-plane, allowing for TC-algorithms that merge TAs across planes, and improve computing performance.
      • This means TA algorithms need to process each TP in less than ~1us.
        • Currently only ADCSimpleWindow & some "number of channels hit" algorithms are that fast.
        • Bigger problem: potential memory leak in the trigger, crashes trigger after ~30 minutes.
      • The ongoing work: online latency measurements, finding the memory leak in the trigger, CPU pinning for the trigger application.
      • Signiicant progress on offline trigger model--still a few things before pushing this to offline groups, but basically all critical pieces for TPC-based triggering are in place.
    • 10:11 10:12
      Activity coordination round table 1m

      Release coordination
      Iceberg
      ND test setups
      EHN1 integration
      SW coordination

      Speakers: Bonnie King (FNAL), John Freeman, Kurt Biery (Fermilab), Patrick Dunne (Imperial College London), Wesley Ketchum (Fermi National Accelerator Laboratory)

      John, Software Coordination:

      • To use the latest-greatest daq-buildtools for v5 development, run "setup_dbt latest_v5" rather than "setup_dbt latest". The latter will give you the latest-greatest for v4 development. For symmetry purposes, "setup_dbt latest_v4" will do the same. 
      • I'm going to be changing the names of some v5 repos today as requested by Alessandro, see my comment on the #daq-oks-integration channel for details
      • I'm going to bump daq-cmake this week, which fixes a problem people sometimes run into when they want to simultaneously develop package A and package C, but package A depends on a Spack-installed package B and package B depends on package C. 
    • 10:12 10:13
      Actions 1m