Release Coordination v5
Iceberg
ND test setups
SW coordination
John, Software Coordination:
CCM
Control
Config
Second session of configuration mini-workshop completed
Light python reader for xml developed for offline software group
Prototype configuration TUI (cider) and other inspection tools merged
Development of demo of git configuration management for NP02
Development of demo of cider shift tool for NP02.
Monitoring
Timing System
Work Package |
Tasks |
Update from last 2 weeks (what activities were completed related to this task) |
Scheduled next 2 weeks (what activities are planned related to this task) |
Status
|
Forecasted End Date (Update in brackets) |
1.1.2 Support CERN operations
|
Preparation for NP02 running. |
|
Continue gathering list of timing endpoints. Continue commissioning GIB and connected fanout unit at CERN. Set up GPS-DO --> GIB --> Fanout chain to provide timing for NP02 (replace with GPS-DO --> GIB --> MIB --> AFC/FIB when available) |
On-track |
01/01/25 |
Consolidate DTS-WR interface |
No update, still waiting response to E-mail to TDE. Work to produce new WR-DTS interface firmware (combine HSI and WR firmware into one design) not started; TDE integration not due until EOY. |
Re-engage with VD TDE. |
Delayed |
1/8/24 (New date uncertain) |
|
Other support |
Timing Units for CRP factories |
Timing units for CRP factories not needed until late next year. Need to port to different FPGA carrier board (Enclustra units go EOL at the end of the month and funding difficult to purchase sufficient units for total needs, which includes setting up test stand for production testing) |
Understand requirements for further units, understand budget constraints |
On-Track |
15/12/24 |
1.1.3 Legacy Software |
Integrating timing with DUNEDAQ 5.x |
Endpoint monitoring features merged to v5.2.1 branches DTS-HSI opmon (re)integration started |
Continue development of DTS-HSI work Plan out v5.2.1/v5.3.0 work |
On-Track |
15/12/24-v5.2.1 release date |
1.3.3.1 MIB Code development/block integration |
Timestamp initialisation from upstream |
MIB firmware initial testes complete, building up software support for new features |
Complete testing and development, merge upstream |
On-track |
16/12/2024 (09/12/2024) |
1.3.1.1 IRIG decoding firmware |
Consolidation |
[No update] waiting on other firmware tasks |
Implement TAI epoch in firmware and software |
On-Hold |
23/12/24 |
1.3.1.2 Fine delay measurement |
Firmware block development |
Work started following addition of FIB v2 firmware support |
Design firmware inter -block interfaces. Design firmware-software interface Integrate fine phase prototype blocks into MIB v2 and AFC designs |
On-track |
16/12/24 |
1.3.6 MIB MMC firmware |
Consolidate MIB MMC firmware |
Continuing debugging discussion with NAT |
Debug hot-swap operation N.B. We could still operate DUNE without hot-swap ability on MIB by power-cycling crate so on hold for now |
On-hold |
(new date uncertain) |
1.4.2.1 Timing Service specifications capture |
Gain document approval |
ST and Pierre presented control proposal and requirements |
Update requirements following presentation, seek approval |
Delayed |
09/12/24 (23/12/24) |
1.2.3.1 FIB pre-production prototype
|
FIB commissioning |
FIB v2 initial testing complete, feature branches merged |
Complete detailed testing of hardware components |
Delayed |
02/12/24 (23/12/24) |
1.2.1.1 GIB pre-production prototype
|
1.2.1.1.4 GIB v2 layout, prep for manufacture and dispatch |
Two quotes received. Discovered issue with component availability. Changed component. Raised requisition. |
Wait for order confirmation with delivery time. Update planning |
Delayed |
22/11/24 (16/12/24) |
1.2.2.1 MIB pre-production prototype |
1.2.2.1.5 MIB pre-production hardware manufacture |
Issues with adding chosen supplier to SBS database. Combination of staff sickness at Hi5 and SBS/STFC slowness. Supplier added to SBS database. Order received and acknowledged |
Completed |
|
3/12/24
|
MIB tongue 2 design |
[No update] |
Design new tongue 2 |
On-track |
23/12/24 |
|
1.7.2.4 “COTS” procurement
|
1.7.2.4.1 - Quote for AFCs
|
Waiting for delivery
|
NA |
Complete |
|
Understand medium term hardware requirements |
Discussion around Enclustra EOL in 2024 |
Make decision on GIB FPGA choice, understand requirements on other Enclustras |
On-track |
23/12/24 |
|
1.7.2.1 procure uTCA items |
Evaluate new uTCA crate. |
[No update] |
Test clock and data fanout |
On-track |
23/12/24 |
1.6.3 Production Readiness Review preparation |
Date and schedule agreement |
UK schedule up to PRR and hardware tasks up to installation updated.Submitted to UK management for comment/update/approval |
Update firmware/software tasks in planning. Integrate with consortium planning |
Delayed |
25/11/24 (23/12/24) |
Trigger: