AD Weekly Friday - 2017 Scheduling Meeting/Weekly Summary (05 May 2017)

Crew Chief

  • See slide. MI transductor electronics issue. Vacuum pump changout on RFQ. Tuning in progress.
Operations Coordinator
  • See Slide.
Linac
  • Referred to the RFQ vacuum pump replacement. Otherwise running well.
Booster
  • See slide. Running well.
Main Injector & Recycler
  • See slides. Discussion about MI-60N ground fault/buss work issues.
NuMI
  • Running well.
NuMI Experiments
  • Running well.
Booster Neutrino
  • Running well.
BNB Experiments
  • Running well.
Muon Rings
  • Working on shunts this morning. May take beam this afernoon. Still a number of things not ready for coasting beam in the Delivery ring. Good news - EE support able to pulse Pmag. Plan to take low power beam to target if applicable.
MTA
  • In between experimental runs, waiting for approval. Cavity is running successfully.
SY120, Neutrino Muon, Meson Test, Meson Center
  • Thanks to MI & MSD for vacuum work in MI-52 region. Tuesday Code 1 at SSB fire alarm for building ceiling heater failure. No damage at SSB other than the heater. Meson beamline off yesterday for experimets install. (M03 & MC6?) Commisioning of M03 exp. went well last night. Thanks to ops for beam setup & tuning. Installed temperature sensor on M01 target. FESS borescoped F2 sump line.
SY120 Experiments
  • Thanks to Michael & Adam for help with M03 experiment installation. Six (6) experiments installed! Maybe a record in MI Fixed target era.
FAST
  • Transverse profile monitor installation continues. Vacuum techs removed xray equipt. from 50 Mev line. Controller board for chiller died. New board installation today. ODH class 1 next week.
PIP-II Injector Test
  • Shutdown continues. Most girders are populated. Meson 3rd cavity installed & under vacuum. Maybe testing next week.
Alignment
  • Provided support for CMTF - Laser scanning.
Controls
  • Repeater power supply failure @ F-27.
Cryo
  • Meson frig is cold. Transfer line is filled with LHe. Vacuum running. Some issues with discharge water pressure, FESS is investigating. Decontam SGC. G-1 wet engine failed. Felts not properly filled with grease. CMTF is cold and running well. NML, FAST Lab B ready. MTA cold and running well.
ES&H
  • MI-12 investigation continues.
EE Support
  • Discussion about the MI transductor electronics replacement. MI 60 S water on floor, 2 hr opt
Instrumentation
  • Found problem with booster toroid, loose solder connection.
Mechanical & Fluids
  • IP829 faulted. MC7 chiller under repair. Under vac today adding refrigerant later.
RF
  • MI, RR & BRF running well.
FESS
  • Awaiting details on Comm Ed switch.
Summer Shutdown 2017
  • Still some manpower issues. Overall in fairly good shape. Short maybe 3 or 4 people. Worklist reminder.
Miscellaneous
  • Discussion on hot Comm Ed switch. See Slides. Main plan - shutdown & access day on Monday May 15th IF schedule holds up.