Shutdown day, accesses + power outage. (good weekend)
Linac
Good weekend. Water pumps cycled for confirmation. Filaments off until this evening. (after second power outage) Linac in stand by.
Booster
Well over the weekend. Friday BRF6 tripped utility yard breaker. Left BRF6 off. Lost BRF11 then turned on BRF6. Still a breaker issue with BRF. BRF17 pulled out due to buss bar work. BRF6 & 11 investigation today.
Booster Neutrino
Running well.
BNB Experiments
Running well. In standby until after 2nd power outage.
Main Injector & Recycler
Good weekend. 520 area vacuum investigation. My change an ion pump.
NuMI
Power glitch on Saturday evening.
NuMI Experiments
In standby mode until 2nd power outage. NOVA is up enough to check fire protection system.
Muon Rings
Successfully send beam to target and secondary beam down M2, M3 & into Delivery ring. Target rotation & motion control not working. PS testing in M5 line. May remove critical device locks tomorrow if ready. Shielding block installation. BV900 stuck. BBP tracking issue, suggested it is a toroid problem.
SY120
Nothing to report.
SY120 Experiments
Mtest running well, no new experiments his week. Lariet will take cosmics during the day. Seaquest installing hotoscopes. SQ has a broken wire in chamber. Will pull today.
ES&H
MI-12 now OK.
EE Support
R:LAM52 over temp investigation.
Mechanical
Techs working on access jobs.
Fluids
Nothing to report.
RF
Booster station #21 buss bar installation. BRF#17 off while installing buss bar. BRF#11 is a bias supply issue. Should come up with full complement of RF excepting BRf#17.
MTA
Nothing to report.
Controls
Recovering from power outage, ready to repeat this afternoon.
Instrumentation
Nothing to report.
FESS
No report.
Miscellaneous
Begin accelerator startup after second power outage and cooling recovery.
There are minutes attached to this event.
Show them.
09:00
→
09:01
Crew Chief Operations Summary1m
Slides
Shutdown day, accesses + power outage. (good weekend)
09:01
→
09:02
Linac1m
Good weekend. Water pumps cycled for confirmation. Filaments off until this evening. (after secon power outage) Linac in stand by.
09:02
→
09:03
Booster1m
Well over the weekend. Friday BRF6 tripped utility yard breaker. Left BRF6 off. Lost BRF11 then turned on BRF6. Still a breaker issue with BRF. BRF17 pulled out due to buss bar work. BRF6 & 11 investigation today.
09:03
→
09:04
Booster Neutrino1m
Running well.
09:04
→
09:13
BNB Experiments9m
Running well. In standby until after 2nd power outage.
09:13
→
09:18
Main Injector & Recycler5m
Good weekend. 520 area vacuum investigation. My change an ion pump.
09:18
→
09:19
NuMI1m
Power glitch on Saturday evening.
09:19
→
09:20
NuMI Experiments1m
In standby mode until 2nd power outage. NOVA is up enough to check fire protection system.
09:20
→
09:21
Muon Rings1m
Successfully send beam to target and secondary beam down M2, M3 & into Delivery ring. Target rotation & motion control not working. PS testing in M5 line. May remove critical device locks tomorrow if ready. Shielding block installation. BV900 stuck. BBP tracking issue, suggested it is a toroid problem.
09:21
→
09:22
SY1201m
Nothing to report.
09:22
→
09:23
SY120 Experiments1m
Mtest running well, no new experiments his week. Lariet will take cosmics during the day. Seaquest installing hotoscopes. SQ has a broken wire in chamber. Will pull today.
09:24
→
09:25
ES&H1m
MI-12 now OK.
09:26
→
09:27
EE Support1m
R:LAM52 over temp investigation.
09:27
→
09:28
Mechanical1m
Techs working on access jobs.
09:28
→
09:29
Fluids1m
Nothing to report.
09:29
→
09:30
RF1m
Booster station #21 buss bar installation. BRF#17 off while installing buss bar. BRF#11 is a bias supply issue. Should come up with full complement of RF excepting BRf#17.
09:30
→
09:31
MTA1m
Nothing to report.
09:31
→
09:32
Controls1m
Recovering from power outage, ready to repeat this afternoon.
09:32
→
09:33
Instrumentation1m
Nothing to report.
09:33
→
09:34
FESS1m
No report.
09:35
→
09:36
Miscellaneous1m
Begin accelerator startup after second power outage and cooling recovery.