LAPPD2 Microchannel Plate Godparent Review

US/Central
A-224 (Argonne, Building 360)

A-224

Argonne, Building 360

Andrey Elagin (Univ. of Chicago), Robert Wagner (Argonne HEP)
    • 08:30 08:45
      Introduction & Overview
      • 08:30
        Review Committee & Participants Introduction 5m
      • 08:35
        Overview of MCP Program 10m
        Speaker: Bob Wagner (Argonne HEPD)
        Slides
    • 08:45 09:45
      Glass Capillary Array Development
      • 08:45
        Capillary Array Development: Status & Plans 30m
        Speaker: Chris Craven (Incom, Inc.)
      • 09:15
        LAPPD Needs, Plans & Requirements for Capillary Arrays 30m
        Speaker: Ossy Siegmund (SSL)
        Slides
    • 09:45 10:30
      ALD Process
      • 09:45
        Status of ALD at Argonne 45m
        Speaker: Anil Mane (Argonne ESD)
    • 10:30 10:45
      Break 15m A-224

      A-224

      Argonne, Building 360

    • 10:45 11:50
      MCP Tests & Results
      • 10:45
        MCP Testing at SSL 30m
        Speaker: Jason McPhate (SSL)
        Slides
      • 11:15
        MCP Testing at APS 25m
        Speaker: Matt Wetstein (UChicago)
        Slides
      • 11:40
        Life Time Studies & Resistance Measurements 10m
        Speaker: Sasha Vostrikov (UChicago)
        Slides
    • 11:50 12:20
      Discussion of Questions
    • 12:20 13:30
      Lunch Break 1h 10m A-224

      A-224

      Argonne, Building 360

    • 13:30 15:15
      MCP Needs & Future Plans
      • 13:30
        MCP Process Flow, Facilities, & Needs 45m
        Speaker: Jeff Elam (Argonne ESD)
        Slides
      • 14:15
        Future Development Plans for ALD 30m
        Speaker: Anil Mane (Argonne ESD)
      • 14:45
        ALD-MCP Schedule, Throughput, & Effort 30m
        Speaker: Jeff Elam (Argonne ESD)
        Slides
    • 15:15 15:30
      Break 15m A-224

      A-224

      Argonne, Building 360

    • 15:30 15:55
      MCP Technology Transfer
      • 15:30
        Technology Transfer of ALD 25m
        Speaker: Aileen O'Mahony (Incom, Inc.)
        Slides
    • 15:55 17:30
      Questions, Draft Report, & Closeout
      • 15:55
        Questions from the Review Committee 20m
      • 16:15
        Review Committee Draft Report 1h
      • 17:15
        Closeout 15m