SY
Timing cable replacement: Installation of replacement cables and conduit underway. Construction to be complete by Sept. 15 17. Adam Done
Rad fencing in F-sector due to construction Adam
VH94 SMPS upgrade: Waiting to commission (need LCW). Adam
Waiting on pond levels to run Remnant LCW system. Adam
Asked MSD to turn on ArCO2 gas systems (TG-8, MS3, and G2) Adam
Startup checklist Adam
Leaky bean pots for septa cables: cleanup coordination Adam and Cons
Secondary containment Paul and Mike
Enclosure DE carboys of old oil Paul and Cons
Meson
MS2LCW pumps
Two pumps down, only one available Paul
Pump #3 has bad motor, waiting on parts.
Pump #2 repaired and run for a brief time.
MSD to size pump and procure hose. Parts ordered. Adam
One level sensor working, fixing the other one. Adam
Upstream M02 leak not repairable without draining system. MSD to tighten valve stem to see if it helps.
MS2LCW head pressure, tank levels. Appears that gas bottle for head pressure is empty, could be cause of level rise. Gordon
MS3 vacuum PLC progress: Mike
Paul A. and Mike to look into installing CT clamps on vacuum pump cables.
Mike getting drawing from Dan, then CTs from Paul K., then installing.
MC6TGT Gordon
Starting up with target in place.
ES&H re-installed grate, locked target box. Replaced back-scatter scintillator. Gordon
MC6D-2
Magnet in place
Power cables and klixons connected
Remaining: MSD working on turning on vacuum pumps, connecting LCW, final LCW leak check when MS2LCW is on, make sure restrictors or regulators are removed
MC6D-4
Check leak once MS2LCW system is back on.
F1 single-point LOTO: work finished. Ops working on config control paperwork approval from ES&H. Paul
Need to remove dehumidifiers (F2 and F3) once MS2LCW up and running. Paul
M01 rad fence needs straightened out, solution with FESS confirmed to not count as excavation (concrete supports). Job finished, waiting on confirmation from ES&H. Tom
Startup checklist Mike
SWIC cable ringer to verify, in particular, MC6WC at low intensity (1E6), check cables. Specs from McArthur, ordering parts. Mike
Can SWICs run in Proportional mode (higher voltage, PWCs?), does polarity matter? From Dan: can go as high as 2200V, no change to polarity. Adam check MCenter Droeges can go this high.
Double-check Tom’s optics for MCenter 120 GeV mode Adam and Mike
NM
Vacuum
All pumps hooked up, downstream pump needs turned on.
NM2 multiwire leaking, Carol following up w/ MSD.
How many interaction lengths at this vacuum level in NM beamline? Carol
NS2LCW, backup pump (pump #2) pending
Carol Believes the parts are in, following up with Greg.
How does the NS2LCW piping run? Pipe is buried across the berm.
NS1LCW system status? Des agrees to have Dan jog the system. Adam
Magnet labels/signs; Enclosure C finished, taking longer than anticipated. Adam and Mike
Some rack labels needed Adam
G2 single-point LOTO electrical work finished. Working with Ops on config control paperwork; waiting on ES&H to approve forms. Paul
NS2LCW sprayers developed a leak, Adam and Kevin about timeline for colder water, help MSD manage manpower.