DOE O 420.2D Phased Reviews: IRR #1a - Common, Support, Linac & MTA
29 Nov 2023, 00:00
→
2 Dec 2023, 18:00
US/Central
IRR 1a - Charge & Charge Questions.pdf
IRR 1a - Charge Letter_for signature_MEC 11-21-2023.pdf
IRR 1a - Schedule.pdf
IRR 1a zoom information.docx
FSO, ARR & Assist Team Comments and Recommendations
20230104_1 FSO to FRA ASE and SAD Comment Resolution Letter.pdf
20230104_2 FERMI ASE and SAD Comment Resolution Form.pdf
20230421_1 COO to FSO Letter - ASE and SAD Comment Resolution Form FRA Response - signed.pdf
20230421_2 FERMI ASE and SAD Comment Resolution Form_FRA Response - FINAL.pdf
20230509 RE_ FRA Response to ASE and SAD Comment Resolution Form.pdf
20230705 COO to FSO Letter - ASE and SAD Comment Resolution Form FRA 2nd Response w. attached - APPROVED.pdf
20230923 ASE Review FSO Comments Final.pdf
20230926 FSO Review of Fermilab ASE Comments rs.pdf
Fermi Outbrief Presentation Recreated Sept 28 2023 4 pm_.pdf
Final- Fermi ARR Report 08-16-2023 (2) (1).pdf
Phased Review Approach Plan
2023_Nov - IRR #1a - Common Support Linac MTA - MQ MS MC_MEC 11-21-2023.pdf
2024_Feb - ARR #1 - Fermi Main Accelerator - MQ MS MC_MEC 11-21-2023.pdf
2024_Jan - IRR #1b - Booster 8 GeV BNB+experiments MI RR NuMI+experiments - MQ MS MC_MEC 11-21-2023.pdf
2024_Jan - IRR #1c - Muon Campus SwitchYard+experiments - MQ MS MC_MEC 11-21-2023.pdf
2024_Jan - IRR #1d - Neutrino Muon+experiments - MQ MS MC_MEC 11-21-2023.pdf
Phased Review Approach to Ensure Readiness to Operate Under DOE O 420.pdf
SAD Section 0 - Title, Approvals, and Table of Content
SAD Section 1 - Overview of Fermilab Facilities
SAD Section 2 - Support Facilities
S02.C01 - Railhead_Rev1_Chapter_20230807.pdf
S02.C01 - Railhead_Rev1_Risk Tables.pdf
S02.C02 - RPCF_Rev1_Chapter&Risk Tables_20230807.pdf
S02.C03 - RAF_Rev1_Chapter_20230806.pdf
S02.C03 - RAF_Rev1_Risk Tables.pdf
S02.C04 - Waste Handling Facilities_Rev1_Chapter_20230802.pdf
S02.C04 - Waste Handling Facilities_Rev1_Risk Tables.pdf
S02.C05 - APS-TD Facilities_Rev1_Chapter_20230809.pdf
S02.C05 - APS-TD Facilities_Rev1_Risk Tables.pdf
S02.C06 - Shipping & Receiving_Rev1_Chapter_20230803.pdf
S02.C06 - Shipping & Receiving_Rev1_Risk Tables.pdf
S02.C07 - Other RMAs_Rev1_Chapter_20230811.pdf
S02.C07 - Other RMAs_Rev1_Risk Tables.pdf
SAD Section 3 - Fermilab Main Accelerator - Accelerator Segments
S03.C01 - Linac_Rev2_Chapter_20231117.pdf
S03.C01 - Linac_Rev2_Risk Tables_20231117.pdf
S03.C02_MTA_Rev3_Chapter_20231120.pdf
S03.C02 - MTA_Rev3_Risk Tables_20231120.pdf
SAD Section 7-A.1 - Accelerator Safety Envelope - Fermilab Main Accelerator
SAD Section 7-B.1 - Fermilab Shielding Policy
SAD Section 7-B.2 - Unreviewed Safety Issue (USI) Program
S07B.2 - Fermi National Accelerator Laboratory Unreviewed Safety Issue (USI) Process - REDLINE DRAFT 20231120.pdf
USI Evaluation Form - REDLINE DRAFT 20231120.pdf
USI Screening Form - REDLINE DRAFT 20231120.pdf
SAD Section 7-C - Non-Accelerator Specific Hazard (NASH) Risk Matrix Tables
Track Changes Version of Documents
S01.C01-C10 - Overview_Rev3_20231121 (1).docx
S03.C01 - Linac_Rev2_Chapter_20231117 (1).docx
S03.C01 - Linac_Rev2_Risk Tables (1).docx
S07A.1 - ASE Fermilab Main Accelerator_Rev13_20231120 IRR1a.docx
Wednesday, 29 November
Tue, 28 Nov
Wed, 29 Nov
Thu, 30 Nov
Executive Session
Welcome
ARR Plan
01. ARR Plan.potx
Addressing FSO, ARR, & Assist Team Comments
02. Addressing Comments.potx
10:00
Coffee Break
Description of SAD/ASE Layout
03. Description of SAD ASE Layout.potx
Description of Fermilab Main Accelerator
04. Description of Fermilab Main Accelerator.potx
Overview of MCI Analysis Methodology
05. Overview of MCI Analysis Methodology.potx
Overview of NASH/1163 Analysis Methodology
06. Overview of NASH Analysis Methodology.potx
12:00
Lunch
USI Process
07. USI Process.potx
ASE Violation Determination & Response
08. ASE Violation Determination & Response.potx
Configuration Management
09. Configuration Management.potx
Interview/Discussion/Executive Session Time
14:30
Coffee Break
Interview/Discussion/Executive Session Time
Daily Debrief
Thursday, 30 November
Tue, 28 Nov
Wed, 29 Nov
Thu, 30 Nov
Executive Session
Credited Control Overview: Part 1
10. Credited Control Overview - All.potx
10:00
Coffee Break
Credited Control Overview: Part 2
10. Credited Control Overview - All.potx
Interview/Discussion/Executive Session Time
12:00
Lunch
Linac Overview
11. Linac Overview.pptx
Linac Tour
14:30
Coffee Break
Interview/Discussion/Executive Session Time
Daily Debrief
Friday, 1 December
Tue, 28 Nov
Wed, 29 Nov
Thu, 30 Nov
Executive Session
MTA Overview
12. MTA Overview.pptx
MTA Tour
10:00
Coffee Break
Interview/Discussion/Executive Session Time
12:00
Lunch Break
Closeout
IRR 1a - Closeout Presentation 12 1 2023.pptx